This documents related to 2024-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2024.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release | Date | Span | Due dates | Notes |
---|---|---|---|---|
2024-09 M1 | Friday, July 12, 2024 | 07/05 to 07/12 |
| 3 weeks from 2024-06 GA |
2024-09 M2 | Friday, August 2, 2024 | 07/26 to 08/02 | 3 weeks from M1 | |
2024-09 M3 | Friday, August 23, 2024 | 08/16 to 08/23 |
| 3 weeks from M2 |
2024-09 RC1 | Friday, August 30, 2024 | 08/23 to 08/30 |
| 1 week from M3 |
2024-09 RC2 | Friday, September 6, 2024 | 08/30 to 09/07 | 1 week from RC1 | |
Quiet period | 09/06 to 09/10 | No builds during "quiet period". It is assumed all code is done by the end of RC2. | ||
2024-09 GA | Wednesday, September 11, 2024 |
| 5 days from RC2 |